| Skip Navigation | Accessible | |||
Metropolitan PoliceAuthority |
Accessibility About MPA Contacts Search | ||
| Home Committees News Partnerships Reports Issues Events Links Your Views | |||
| Committees > MPA > 27 Feb 03 > Airwave - ready for service date | |||
|
QuickSearch |
|||
|
Page summary This resource is from the Committees section. This is report 13 of the 27 Feb 03 meeting of the MPA Committee and sets out the rationale for having the Airwave service available for MPS use as from 1 October 2003 and recommends that this date be contractually agreed. Sections available here: Content Airwave - ready for service date Report: 13 SummaryThis report sets out the rationale for having the Airwave service available for MPS use as from 1 October 2003 and recommends that this date be contractually agreed. A. RecommendationThat the Authority agrees a ready for service date for Airwave of 1 October 2003. B. Supporting information1. Under the terms of the Airwave contract, O2 is required to provide and the MPS is required to take the Airwave service in the 4th quarter of 2003. The exact date is the subject of negotiation between the MPA, MPS, PITO and O2 but the Ready For Service (RFS) date triggers payment for core and menu exclusive services. With the support of the others mentioned, O2 have now written to the Authority proposing an RFS date of 1 October 2003. As from that date a monthly revenue payment of £2,500,000 to O2 becomes due but is borne by PITO. The Authority will incur the cost of the menu exclusive service which, at the start of the service, equates to a charge of approximately £110,000 per month. Both of these costs will be met from the SR2000 grant allocated for Airwave by the Home Office. Technically, the Home Office could recover any monies set aside for Airwave payments which remain unused, though they are unlikely to do so. 2. At the outset of the project a date of 15 December 2003 was tentatively proposed as being the latest RFS date acceptable to all parties. As the Airwave project progressed, understanding of what can be achieved by the contractor and what needs to be addressed by the MPS has improved. Much of this has been through the learning from other forces that have already taken the Airwave service and the MPS experience of providing a trunked radio system (Metradio). 3. Over the past year, O2 have demonstrated that they are capable of achieving the earliest RFS date of 1 October for the MPS and within their own plans have been working towards this objective. This has been possible through a significant re-organisation of their approach to the national programme and the introduction of appropriate calibre of staff to address the MPS requirement. A comprehensive review of the O2 Airwave plan for the London region by PITO and subsequently by the MPS airwave project team has concluded that the O2 plan is robust, sustainable and achievable. 4. In examining possible RFS dates the following internal issues and drivers have been taken into account.
5. In summary, for operational and contractual reasons the RFS date must fall during October 2003. There are no direct financial implications for the Authority if RFS is at the start or end of the month but an RFS date of 1 October 2003 will mitigate the threats to project planning and operational implementation. The integration of Airwave is critical to the successful implementation of C3i. If approved, the commitment will be signed off by the Clerk. C. Equality and diversity implicationsNone. D. Financial implicationsAs set out in body of report. E. Background papersNone. F. Contact detailsReport author: Keith Dickinson, MPA For more information contact:
MPA general: 020 7202 0202 |
|||
| Committees > MPA > 27 Feb 03 > Airwave - ready for service date | |||
|
© Copyright 2002-2008, Metropolitan Police Authority. | Terms & Conditions | Privacy | Freedom of Information |
|||